Revamp for Cryogenic Plants CPUI, KPUI and KPUII
Client: Safer Exploration , Production & Operations Company
Project Type: Basic and Detail Design
Project Location: Republic of Yemen
Project Status: In progress

Project Summary:
  • The capacity expansion from 420 mmscfd to 520 mmscfd for three cryogenic plants CPU I, KPUI and KPUII
  • The residue gas must upgrade and meet the Yemen LPG feed gas specification

Project Responsibility:

  • Expansion plan study and selection
  • Cost investment analysis
  • Design basis and design philosophy generation
  • Check and verification of existing equipments, electrical, utility system
  • RFQ Package development and bid evaluation
  • Basic design for the modification
  • Detail design for the modification
  • Commission, operation manual Technical support for construction and commission

Project Highlights:

  • Strict high heat value specification for residue gas product of the plants
  • Optimization to maximum product output with minimum investment

Contract Award Date: June 2007

 